Red Sea Project

In cooperation with Blumberg Engineers, Sievertconsult was the specialized reed bed consultant for the detailed design of a reed bed for up to 16.000 m³/day waste water generated from various locations in the Red Sea Project (Hotels, camps, etc.).

While the system is still under construction (August 2022) the first section (Phase 0) for up to 6000 m³/day is already under operation and produces treated effluent which is used as irrigation water for the nursery of the project.

The fast construction, start-up and partly operation, even during construction, is possible due to the modular design of the system with single units (total 130 reed bed basins), each for 250 m³/day.